Main Dam Package |
Dams |
Depletion Channel |
Earthwork |
L.Cum |
3.31 |
1.95 |
58.91 |
Civil & HM works of Depletion sluice at Ch. 1648 m of DSCD was substantially completed. |
Depletion Channel |
Concrete |
|
2560.00 |
1270.00 |
49.61 |
None |
Depletion Channel |
Gates (Supply & Fabrication) |
mt |
46.47 |
15.13 |
32.56 |
None |
Depletion Channel |
Gates (Erection) |
mt |
46.47 |
15.13 |
32.56 |
Completed |
New parallel Diaphragm Wall (Gap- II) |
Concrete |
Sqm |
50300.00 |
15114.00 |
30.05 |
Construction commenced and in progress. |
Buttress |
Embankment |
L.Cum |
8.90 |
7.11 |
79.89 |
In progress |
Upstream Coffer Dam |
Embankment |
L.Cum |
61.70 |
61.70 |
100.00 |
Work completed |
Downstream Coffer Dam |
Embankment |
L.Cum |
46.01 |
36.06 |
78.37 |
Embankment work completed. Balance rip rap on river side, rock toe & toe drain is pending. |
ECRF Dam (Gap-I) |
Embankment |
L.Cum |
11.40 |
0.00 |
0.00 |
Stockpiling of material is in progress. |
Diaphragm Wall (Gap-I) |
Concrete |
|
393.40 |
393.40 |
100.00 |
Completed |
ECRF Dam (Gap-II) |
Embankment |
L.Cum |
104.72 |
19.91 |
19.01 |
Material Investigations & designs in progress. |
Concrete Dam (GAP-III) |
Concrete |
L.Cum |
0.23 |
0.25 |
108.70 |
Completed. |
ECRF Dam (Gap-I) |
Vibro Stone Columns |
|
1.47 |
1.34 |
90.79 |
Based on the test results of Piezocone & Oedometer, PoE suggested that further VSC is not required. Design of Dam in progress. |
ECRF Dam (Gap-I) |
Deep Soil Mixing |
|
0.84 |
0.84 |
99.17 |
Completed |
ECRF Dam (Gap-I) |
Excavation |
L.Cum |
0.99 |
0.00 |
0.00 |
As suggested by GSI, excavation for G' Hill and D Hill abutments up to desired level under progress and subsequent groutability tests need to be carried out. |
ECRF Dam (Gap-II) |
Sand Densification |
L.Cum |
34.40 |
33.71 |
97.99 |
In progress |
ECRF Dam (Gap-II) |
Deep Soil Mixing |
|
0.39 |
0.00 |
0.00 |
Methodology is under preparation. |
Concrete Dam (Gap-III) |
Excavation |
L.Cum |
0.28 |
0.28 |
100.00 |
Completed |
Concrete Dam (Gap-III) |
Steel |
mt |
137.79 |
127.79 |
92.74 |
Completed |
Spillway |
Approach Channel |
Excavation |
L.Cum |
186.88 |
154.90 |
82.89 |
Currently, work on hold due to flow of water in river. |
Spillway (Structure) |
Concrete |
L.Cum |
18.15 |
17.66 |
97.30 |
Completed |
Fish Ladder |
Fish Ladder |
|
4.00 |
4.00 |
100.00 |
Erection of gates is on hold for want of approved drawing of rope drum hoist from CWC. |
Spill Channel |
Concrete |
L.Cum |
18.20 |
15.13 |
83.13 |
None |
Radial Gates |
Gates |
|
48.00 |
48.00 |
100.00 |
Completed |
Guide Bund |
Embankment |
L.Cum |
8.78 |
8.76 |
99.72 |
Work completed. Rectification measures to partial damages occurred during 2023 is to be finalized. |
Spillway (Structure) |
Earthwork |
L.Cum |
51.70 |
50.08 |
96.87 |
Completed |
Spillway (Structure) |
Steel |
mt |
60336.31 |
56083.51 |
92.95 |
None |
Spill Channel |
Earthwork |
L.Cum |
661.50 |
622.37 |
94.08 |
On hold |
Spill Channel |
Embankment |
L.Cum |
20.36 |
7.34 |
36.04 |
None |
Pilot Channel |
Earthwork |
L.Cum |
49.99 |
24.28 |
48.57 |
On hold due to submergence of working area. |
Right Connectivity |
Package No. 62 |
Head Regulator (P) |
Earthwork + Embankment |
L.Cum |
6.29 |
6.29 |
100.00 |
Completed |
Head Regulator (P) |
Gates |
Sqm |
531.00 |
531.00 |
100.00 |
Completed |
Saddle Dam E |
Concrete |
L.Cum |
0.10 |
0.10 |
100.00 |
Completed |
Saddle Dam E |
Gates |
Sqm |
23.80 |
23.80 |
100.00 |
Completed |
Saddle Dam F |
Concrete |
L.Cum |
0.04 |
0.04 |
100.00 |
Completed |
Saddle Dam F |
Gates |
Sqm |
22.46 |
22.46 |
100.00 |
Completed except few HM works of Depletion Sluice. |
Off-take Regulator |
Earthwork |
L.Cum |
0.96 |
0.96 |
100.00 |
Completed |
Off-take Regulator |
Gates |
Sqm |
402.00 |
402.00 |
100.00 |
Completed |
Head Regulator (P) |
Concrete |
L.Cum |
0.58 |
0.58 |
100.00 |
Completed |
Saddle Dam E |
Earthwork + Embankment |
L.Cum |
8.83 |
8.83 |
100.00 |
Completed |
Saddle Dam F |
Earthwork + Embankment |
L.Cum |
3.07 |
3.07 |
100.00 |
Package 3 60(C): No progress during the Reporting Month |
Off-take Regulator |
Concrete |
L.Cum |
0.21 |
0.21 |
100.00 |
Completed |
Package No. 63 |
Twin Tunnels |
Earthwork |
L.Cum |
2.55 |
2.07 |
81.18 |
Demucking at left & right tube in progress. |
Exit Channel |
Earthwork |
L.Cum |
1.20 |
0.79 |
65.83 |
Mucking in progress. |
Exit Channel |
Concrete |
L.Cum |
0.01 |
0.00 |
0.00 |
No Progress during the reporting month. |
Entry Channel |
Earthwork |
L.Cum |
1.86 |
1.18 |
63.44 |
Mucking in progress. |
Entry Channel |
Concrete |
L.Cum |
0.01 |
0.00 |
0.00 |
Not started. |
Twin Tunnels |
Lining |
L.Cum |
0.60 |
0.00 |
0.00 |
Concreting in both left & right tubes in progress. |
Bunds |
Embankment |
L.Cum |
2.55 |
2.55 |
100.00 |
No Progress during the reporting month. |
Bunds |
Concrete |
|
2336.00 |
1385.00 |
59.29 |
No Progress during the reporting month. |
Package No. 64 |
Twin Tunnels |
Earthwork |
L.Cum |
2.74 |
2.60 |
94.89 |
Excavation as per TAC approval substantially completed. |
Exit Channel |
Earthwork |
L.Cum |
6.02 |
5.51 |
91.53 |
Mucking in progress. |
Exit Channel |
Concrete |
L.Cum |
0.11 |
0.00 |
0.00 |
Not started |
Entry Channel |
Concrete |
L.Cum |
0.01 |
0.00 |
0.00 |
None |
Entry Channel |
Earthwork |
L.Cum |
2.21 |
2.21 |
100.00 |
None |
Twin Tunnels |
Lining |
L.Cum |
0.58 |
0.18 |
31.03 |
None |
Left Connectivity |
Package No. 65 |
Approach Channel-I & II |
Earthwork |
L.Cum |
18.93 |
16.89 |
89.22 |
"Approach Channel I: Presently work on hold.
Approach Channel II: Works in progress." |
Head Regulator |
Concrete |
L.Cum |
0.61 |
0.24 |
39.34 |
Concreting in progress. |
Navigation Lock/Navigation Chamber |
Concrete |
L.Cum |
0.12 |
0.00 |
0.00 |
Presently Works on hold and planned to be taken up in Phase-II of the Project. |
Irrigation Tunnel |
Lining |
|
86400.00 |
10347.00 |
11.98 |
Bed concreting in progress. |
Navigation Channel |
Concrete |
L.Cum |
0.07 |
0.00 |
0.00 |
Presently Works were on hold and planned to be taken up in Phase-II of the Project. |
Approach Channel-I & II |
Concrete |
|
0.21 |
0.00 |
0.00 |
None |
Head Regulator |
Earthwork |
L.Cum |
3.16 |
2.92 |
92.29 |
None |
Head Regulator |
Steel |
mt |
1412.00 |
269.82 |
19.11 |
None |
Head Regulator |
Gates |
mt |
1192.00 |
0.00 |
0.00 |
None |
Navigation Lock/Navigation Chamber |
Earthwork |
L.Cum |
0.49 |
0.38 |
77.55 |
Presently Works on hold and planned to be taken up in Phase-II of the Project. |
Navigation Lock/Navigation Chamber |
Steel |
mt |
618.00 |
0.00 |
0.00 |
None |
Navigation Lock/Navigation Chamber |
Gates |
mt |
55.00 |
0.00 |
0.00 |
None |
Irrigation Tunnel |
Earthwork |
L.Cum |
3.95 |
3.39 |
85.82 |
Second stage benching completed from Ch. 1956 m to Ch. 2780 m. |
Irrigation Tunnel |
Steel |
mt |
3599.17 |
440.30 |
12.23 |
None |
Navigation Channel |
Earthwork |
L.Cum |
2.76 |
2.59 |
93.57 |
None |
Navigation Channel |
Steel |
mt |
0.16 |
0.00 |
0.00 |
On Hold |
Exit Channel |
Earthwork |
L.Cum |
4.22 |
3.55 |
83.96 |
No Progress during the reporting month. |
Exit Channel |
Concrete |
L.Cum |
0.02 |
0.00 |
0.00 |
None |
Package No. 66 |
Saddle Dam KL |
Embankment |
L.Cum |
21.28 |
16.18 |
76.03 |
Work in progress. |
Navigation Tunnel |
Lining |
L.Cum |
0.56 |
0.12 |
21.43 |
Presently Works on hold and planned to be taken up in Phase-II of the Project. |
Saddle Dam KL |
Earthwork |
L.Cum |
3.09 |
2.55 |
82.52 |
None |
Navigation Tunnel |
Steel |
mt |
898.00 |
0.00 |
0.00 |
None |
Exit Channel |
Earthwork |
L.Cum |
3.09 |
2.68 |
86.73 |
No Progress during the reporting month. |
Exit Channel |
Concrete |
|
500.00 |
0.00 |
0.00 |
None |
Saddle Dam KL |
Concrete |
|
5332.00 |
2709.00 |
50.81 |
No progress during the reporting month. |
Depletion Sluice at km 1.575 of Saddle Dam |
Earthwork |
|
4886.00 |
4200.00 |
85.96 |
No Progress during the reporting month. |
Depletion Sluice at km 1.575 of Saddle Dam |
Concrete |
|
4746.00 |
441.00 |
9.29 |
Concreting in progress. |
Depletion Sluice at km 1.575 of Saddle Dam |
Steel |
mt |
510.00 |
27.87 |
5.46 |
None |
Open Cut |
Earthwork |
L.Cum |
3.98 |
2.64 |
66.33 |
No Progress during the reporting month. |
Open Cut |
Concrete |
L.Cum |
0.02 |
0.00 |
0.00 |
None |
Package No. 67 |
Navigation Canal |
Lining |
L.Cum |
0.14 |
0.01 |
7.14 |
Presently Works on hold and planned to be taken up in Phase-II of the Project. |
Navigation Canal |
Earthwork |
L.Cum |
7.88 |
6.33 |
80.29 |
None |
High Head Locks (1, 2 & 3) |
Concrete |
L.Cum |
0.75 |
0.70 |
92.59 |
None |
High Head Locks (1, 2 & 3) |
Gates |
Sqm |
1521.56 |
622.00 |
40.88 |
None |
LMC Package Wise |
Package No. 1 |
Package 1 includes Pkg- 1A: Part work Pkg- 1B: Essential works Pkg- 1C: Non-essential works |
Earthwork |
L.Cum |
214.00 |
209.88 |
98.07 |
"Package 1 : Terminated /Pre-closed.
Package 1(A): Completed." |
Package 1 includes Pkg- 1A: Part work Pkg- 1B: Essential works Pkg- 1C: Non-essential works |
Lining |
L.Cum |
2.50 |
1.58 |
63.20 |
Package 1(B): works in progress. |
Package 1 includes Pkg- 1A: Part work Pkg- 1B: Essential works Pkg- 1C: Non-essential works |
Structures |
|
50.00 |
25.00 |
50.00 |
Package 1(C): Tenders to be called. |
Package No. 2 |
Package 2 Includes Pkg- 2A: NH Crossing near Murari Village (km 33.559) Pkg- 2B: NH Crossing near Mallepalli Village (km 41.56) |
Earthwork |
L.Cum |
213.27 |
212.63 |
99.70 |
Package 2: Work completed |
Package 2 Includes Pkg- 2A: NH Crossing near Murari Village (km 33.559) Pkg- 2B: NH Crossing near Mallepalli Village (km 41.56) |
Lining |
L.Cum |
2.15 |
2.13 |
99.07 |
Package 2(A): Work restarted |
Package 2 Includes Pkg- 2A: NH Crossing near Murari Village (km 33.559) Pkg- 2B: NH Crossing near Mallepalli Village (km 41.56) |
Structures |
|
42.00 |
41.00 |
97.62 |
Package 2(B): Work completed |
Package No. 3 |
Package 3 Includes Pkg- 3A: Part work Pkg- 3B: Burugupudi NH Crossing Pkg- 3C: Prathipadu NH Crossing Pkg- 3D: Balance essential works Pkg- 3E: Non-essential works |
Earthwork |
L.Cum |
117.75 |
109.19 |
92.73 |
"Package 3: Terminated /Pre-closed.
Package 3(A): Work in progress" |
Package 3 Includes Pkg- 3A: Part work Pkg- 3B: Burugupudi NH Crossing Pkg- 3C: Prathipadu NH Crossing Pkg- 3D: Balance essential works Pkg- 3E: Non-essential works |
Lining |
L.Cum |
1.57 |
1.32 |
84.08 |
"Package 3(B): Work Completed.
Package 3(C): Work in progress." |
Package 3 Includes Pkg- 3A: Part work Pkg- 3B: Burugupudi NH Crossing Pkg- 3C: Prathipadu NH Crossing Pkg- 3D: Balance essential works Pkg- 3E: Non-essential works |
Structures |
|
48.00 |
19.00 |
39.58 |
"Package 3(D): Works in progress.
Package 3(E): Tenders to be called." |
Package No. 4 |
Package 4 Includes Pkg- 4A: Part work Pkg- 4B: Chendurthi NH Crossing Pkg- 4C: Bendapudi NH Crossing -Pkg- 4D: Arempudi NH Crossing Pkg- 4E: Kathipudi NH Crossing Pkg- 4F: Balance essential works |
Earthwork |
L.Cum |
131.73 |
127.35 |
96.68 |
"Package 4: Agency has given consent for preclosure of contract.
Package 4(A): No progress during the Reporting Month" |
Package 4 Includes Pkg- 4A: Part work Pkg- 4B: Chendurthi NH Crossing Pkg- 4C: Bendapudi NH Crossing -Pkg- 4D: Arempudi NH Crossing Pkg- 4E: Kathipudi NH Crossing Pkg- 4F: Balance essential works |
Lining |
L.Cum |
2.10 |
1.65 |
78.57 |
Package 4(B), 4(C), 4(D) & 4(E): Work in progress during the Reporting Month. |
Package 4 Includes Pkg- 4A: Part work Pkg- 4B: Chendurthi NH Crossing Pkg- 4C: Bendapudi NH Crossing -Pkg- 4D: Arempudi NH Crossing Pkg- 4E: Kathipudi NH Crossing Pkg- 4F: Balance essential works |
Structures |
|
47.00 |
5.00 |
10.64 |
Package 4(F): Agreement concluded on 18-Mar-2025 and work in progress. |
Package No. 5 |
Package 5 Includes Pkg- 5A: Part work Pkg- 5B: Gavarayya Koneru NH Crossing Pkg- 5C: Balance essential works (KM 93.700 to 111.000+0.487KM) Pkg- 5D: Balance non-essential works (KM 93.700 to 111.000+0.487KM) |
Earthwork |
L.Cum |
204.45 |
154.42 |
75.53 |
"Package 5 & 5(A): Terminated /Pre-closed.
Package 5(B): No progress during reporting month." |
Package 5 Includes Pkg- 5A: Part work Pkg- 5B: Gavarayya Koneru NH Crossing Pkg- 5C: Balance essential works (KM 93.700 to 111.000+0.487KM) Pkg- 5D: Balance non-essential works (KM 93.700 to 111.000+0.487KM) |
Lining |
L.Cum |
1.49 |
0.85 |
57.05 |
Package 5(C): works in progress. |
Package 5 Includes Pkg- 5A: Part work Pkg- 5B: Gavarayya Koneru NH Crossing Pkg- 5C: Balance essential works (KM 93.700 to 111.000+0.487KM) Pkg- 5D: Balance non-essential works (KM 93.700 to 111.000+0.487KM) |
Structures |
|
47.00 |
11.00 |
23.40 |
Package 5(D): Tenders to be called. |
Package No. 6 |
Package 6 components: Pkg- 6A: Part work Pkg- 6B: Balance essential works Pkg- 6C: Balance non-essential works Pkg- 60C: Balance leftover earthwork quantity |
Structures |
|
83.00 |
24.00 |
28.92 |
Package 6 60(C): Work in progress. |
Package 6 components: Pkg- 6A: Part work Pkg- 6B: Balance essential works Pkg- 6C: Balance non-essential works Pkg- 60C: Balance leftover earthwork quantity |
Earthwork |
L.Cum |
169.12 |
143.49 |
84.85 |
"Package 6: No progress during the reporting month.
Package 6(A): Terminated/Pre-closed." |
Package 6 components: Pkg- 6A: Part work Pkg- 6B: Balance essential works Pkg- 6C: Balance non-essential works Pkg- 60C: Balance leftover earthwork quantity |
Lining |
L.Cum |
2.06 |
1.50 |
72.82 |
"Package 6(B): Works in progress.
Package 6(C): Tenders yet to be called." |
Package No. 7 |
Package 7 |
Earthwork |
L.Cum |
100.83 |
99.52 |
98.70 |
None |
Package 7 |
Lining |
L.Cum |
1.87 |
1.70 |
90.91 |
None |
Package 7 |
Structures |
|
68.00 |
38.00 |
55.88 |
Work in progress. |
Package 7(A) |
Earthwork |
L.Cum |
51.73 |
51.73 |
100.00 |
None |
Package No. 8 |
Package 8 components: Pkg- 8A & 8B: Part works Pkg- 8C: Balance essential works Pkg- 8D: Balance non-essential works Pkg- 8E: Pisinikada NH Crossing Pkg- 8F: Railway Crossing |
Earthwork |
L.Cum |
24.79 |
17.85 |
72.00 |
"Package 8, 8(A) & 8(B): Terminated/pre-closed.
Package 8(C): Agreement for balance essential works concluded" |
Package 8 components: Pkg- 8A & 8B: Part works Pkg- 8C: Balance essential works Pkg- 8D: Balance non-essential works Pkg- 8E: Pisinikada NH Crossing Pkg- 8F: Railway Crossing |
Lining |
L.Cum |
0.88 |
0.23 |
26.14 |
"Package 8(D): Tenders yet to be called.
Package 8(E): Contract award to be done" |
Package 8 components: Pkg- 8A & 8B: Part works Pkg- 8C: Balance essential works Pkg- 8D: Balance non-essential works Pkg- 8E: Pisinikada NH Crossing Pkg- 8F: Railway Crossing |
Structures |
|
76.00 |
3.00 |
3.95 |
Package 8(F): GAD approved and estimates to be prepared and submitted. |
RMC Package Wise |
Package No. 1 |
Package 1 |
Earthwork |
L.Cum |
167.75 |
167.75 |
100.00 |
Work completed |
Package 1 |
Lining |
L.Cum |
1.61 |
1.61 |
100.00 |
None |
Package 1 |
Structures |
|
24.00 |
24.00 |
100.00 |
Package 6 60(C): Work in progress. |
Package No. 2 |
Including Package 2 & Package 2 60(C) |
Earthwork |
L.Cum |
203.46 |
203.46 |
100.00 |
None |
Including Package 2 & Package 2 60(C) |
Lining |
L.Cum |
3.28 |
3.09 |
94.21 |
No progress during this month |
Including Package 2 & Package 2 60(C) |
Structures |
|
31.00 |
28.00 |
90.32 |
None |
Package No. 3 |
Including Package 3 & Package 3 60(C) |
Earthwork |
L.Cum |
234.79 |
234.79 |
100.00 |
Package 3: Work completed |
Including Package 3 & Package 3 60(C) |
Lining |
L.Cum |
3.07 |
3.07 |
100.00 |
Package 3 60(C): No progress during the Reporting Month |
Including Package 3 & Package 3 60(C) |
Structures |
|
39.00 |
38.00 |
97.44 |
Work in progress. |
Package No. 4 |
Including Package 4 & Package 4 60(C) |
Earthwork |
L.Cum |
219.20 |
219.20 |
100.00 |
Package 4: Work completed |
Including Package 4 & Package 4 60(C) |
Lining |
L.Cum |
3.66 |
3.64 |
99.45 |
Package 4 60(C): Work in Progress during the reporting month |
Including Package 4 & Package 4 60(C) |
Structures |
|
45.00 |
44.00 |
97.78 |
None |
Package No. 5 |
Including Package 5 & Package 5 60(C) |
Earthwork |
L.Cum |
124.19 |
124.19 |
100.00 |
None |
Including Package 5 & Package 5 60(C) |
Lining |
L.Cum |
2.96 |
2.67 |
90.20 |
No progress during this month |
Including Package 5 & Package 5 60(C) |
Structures |
|
54.00 |
35.00 |
64.81 |
None |
Package No. 6 |
Including Package 6 & Package 6 60(C) |
Earthwork |
L.Cum |
116.94 |
116.94 |
100.00 |
None |
Including Package 6 & Package 6 60(C) |
Lining |
L.Cum |
2.23 |
2.04 |
91.48 |
No progress during this month |
Including Package 6 & Package 6 60(C) |
Structures |
|
34.00 |
22.00 |
64.71 |
None |
Package No. 7 |
Package 7 |
Earthwork |
L.Cum |
66.61 |
66.61 |
100.00 |
Work completed |
Package 7 |
Lining |
L.Cum |
1.03 |
1.03 |
100.00 |
None |
Package 7 |
Structures |
|
15.00 |
15.00 |
100.00 |
None |
Package 7(A) |
Lining |
L.Cum |
1.42 |
0.90 |
63.38 |
No progress during this month |
Package 7(A) |
Structures |
|
13.00 |
8.00 |
61.54 |
None |