Polavaram Project Authority
 
Swatch Bharat Abhiyan
Ministry of Jal Shakti

See your progress, understand your performance

  • Physical & Financial Progress
  • Progress of R&R Works
  • Funds Released by GoI
  • Flow Chart of Proposals Reimbursement

Detailed Physical Progress of Civil Works

As on: 31-05-2025
Component Sub Component Unit Total Quantity Executed Quantity Progress (%)
Headworks
Concrete L.Cum 44.51 37.28 83.76
Steel mt 77744.29 66004.37 84.90
Right Main Canal
Earthwork L.Cum 1184.67 1184.67 100.00
Lining L.Cum 19.25 18.05 93.77
Structures 255.00 214.00 83.92
Left Main Canal
Earthwork L.Cum 1174.79 1074.34 91.45
Lining L.Cum 14.62 10.97 75.03
Structures 461.00 166.00 36.01
Total PIP
Concrete L.Cum 44.51 37.28 83.76
Steel mt 77744.29 66004.37 84.90
Earthwork L.Cum 2359.46 2259.01 95.74
Lining L.Cum 33.87 29.02 85.68
Structures 716.00 380.00 53.07

Progress of Sub-Components under Headworks

Component Sub Component Item Sub Item Unit Total Quantity Executed Quantity Completed (%) Remarks
Main Dam Package Dams Depletion Channel Earthwork L.Cum 3.31 1.95 58.91 Civil & HM works of Depletion sluice at Ch. 1648 m of DSCD was substantially completed.
Depletion Channel Concrete 2560.00 1270.00 49.61 None
Depletion Channel Gates (Supply & Fabrication) mt 46.47 15.13 32.56 None
Depletion Channel Gates (Erection) mt 46.47 15.13 32.56 Completed
New parallel Diaphragm Wall (Gap- II) Concrete Sqm 50300.00 15114.00 30.05 Construction commenced and in progress.
Buttress Embankment L.Cum 8.90 7.11 79.89 In progress
Upstream Coffer Dam Embankment L.Cum 61.70 61.70 100.00 Work completed
Downstream Coffer Dam Embankment L.Cum 46.01 36.06 78.37 Embankment work completed. Balance rip rap on river side, rock toe & toe drain is pending.
ECRF Dam (Gap-I) Embankment L.Cum 11.40 0.00 0.00 Stockpiling of material is in progress.
Diaphragm Wall (Gap-I) Concrete 393.40 393.40 100.00 Completed
ECRF Dam (Gap-II) Embankment L.Cum 104.72 19.91 19.01 Material Investigations & designs in progress.
Concrete Dam (GAP-III) Concrete L.Cum 0.23 0.25 108.70 Completed.
ECRF Dam (Gap-I) Vibro Stone Columns 1.47 1.34 90.79 Based on the test results of Piezocone & Oedometer, PoE suggested that further VSC is not required. Design of Dam in progress.
ECRF Dam (Gap-I) Deep Soil Mixing 0.84 0.84 99.17 Completed
ECRF Dam (Gap-I) Excavation L.Cum 0.99 0.00 0.00 As suggested by GSI, excavation for G' Hill and D Hill abutments up to desired level under progress and subsequent groutability tests need to be carried out.
ECRF Dam (Gap-II) Sand Densification L.Cum 34.40 33.71 97.99 In progress
ECRF Dam (Gap-II) Deep Soil Mixing 0.39 0.00 0.00 Methodology is under preparation.
Concrete Dam (Gap-III) Excavation L.Cum 0.28 0.28 100.00 Completed
Concrete Dam (Gap-III) Steel mt 137.79 127.79 92.74 Completed
Spillway Approach Channel Excavation L.Cum 186.88 154.90 82.89 Currently, work on hold due to flow of water in river.
Spillway (Structure) Concrete L.Cum 18.15 17.66 97.30 Completed
Fish Ladder Fish Ladder 4.00 4.00 100.00 Erection of gates is on hold for want of approved drawing of rope drum hoist from CWC.
Spill Channel Concrete L.Cum 18.20 15.13 83.13 None
Radial Gates Gates 48.00 48.00 100.00 Completed
Guide Bund Embankment L.Cum 8.78 8.76 99.72 Work completed. Rectification measures to partial damages occurred during 2023 is to be finalized.
Spillway (Structure) Earthwork L.Cum 51.70 50.08 96.87 Completed
Spillway (Structure) Steel mt 60336.31 56083.51 92.95 None
Spill Channel Earthwork L.Cum 661.50 622.37 94.08 On hold
Spill Channel Embankment L.Cum 20.36 7.34 36.04 None
Pilot Channel Earthwork L.Cum 49.99 24.28 48.57 On hold due to submergence of working area.
Right Connectivity Package No. 62 Head Regulator (P) Earthwork + Embankment L.Cum 6.29 6.29 100.00 Completed
Head Regulator (P) Gates Sqm 531.00 531.00 100.00 Completed
Saddle Dam E Concrete L.Cum 0.10 0.10 100.00 Completed
Saddle Dam E Gates Sqm 23.80 23.80 100.00 Completed
Saddle Dam F Concrete L.Cum 0.04 0.04 100.00 Completed
Saddle Dam F Gates Sqm 22.46 22.46 100.00 Completed except few HM works of Depletion Sluice.
Off-take Regulator Earthwork L.Cum 0.96 0.96 100.00 Completed
Off-take Regulator Gates Sqm 402.00 402.00 100.00 Completed
Head Regulator (P) Concrete L.Cum 0.58 0.58 100.00 Completed
Saddle Dam E Earthwork + Embankment L.Cum 8.83 8.83 100.00 Completed
Saddle Dam F Earthwork + Embankment L.Cum 3.07 3.07 100.00 Package 3 60(C): No progress during the Reporting Month
Off-take Regulator Concrete L.Cum 0.21 0.21 100.00 Completed
Package No. 63 Twin Tunnels Earthwork L.Cum 2.55 2.07 81.18 Demucking at left & right tube in progress.
Exit Channel Earthwork L.Cum 1.20 0.79 65.83 Mucking in progress.
Exit Channel Concrete L.Cum 0.01 0.00 0.00 No Progress during the reporting month.
Entry Channel Earthwork L.Cum 1.86 1.18 63.44 Mucking in progress.
Entry Channel Concrete L.Cum 0.01 0.00 0.00 Not started.
Twin Tunnels Lining L.Cum 0.60 0.00 0.00 Concreting in both left & right tubes in progress.
Bunds Embankment L.Cum 2.55 2.55 100.00 No Progress during the reporting month.
Bunds Concrete 2336.00 1385.00 59.29 No Progress during the reporting month.
Package No. 64 Twin Tunnels Earthwork L.Cum 2.74 2.60 94.89 Excavation as per TAC approval substantially completed.
Exit Channel Earthwork L.Cum 6.02 5.51 91.53 Mucking in progress.
Exit Channel Concrete L.Cum 0.11 0.00 0.00 Not started
Entry Channel Concrete L.Cum 0.01 0.00 0.00 None
Entry Channel Earthwork L.Cum 2.21 2.21 100.00 None
Twin Tunnels Lining L.Cum 0.58 0.18 31.03 None
Left Connectivity Package No. 65 Approach Channel-I & II Earthwork L.Cum 18.93 16.89 89.22 "Approach Channel I: Presently work on hold. Approach Channel II: Works in progress."
Head Regulator Concrete L.Cum 0.61 0.24 39.34 Concreting in progress.
Navigation Lock/Navigation Chamber Concrete L.Cum 0.12 0.00 0.00 Presently Works on hold and planned to be taken up in Phase-II of the Project.
Irrigation Tunnel Lining 86400.00 10347.00 11.98 Bed concreting in progress.
Navigation Channel Concrete L.Cum 0.07 0.00 0.00 Presently Works were on hold and planned to be taken up in Phase-II of the Project.
Approach Channel-I & II Concrete 0.21 0.00 0.00 None
Head Regulator Earthwork L.Cum 3.16 2.92 92.29 None
Head Regulator Steel mt 1412.00 269.82 19.11 None
Head Regulator Gates mt 1192.00 0.00 0.00 None
Navigation Lock/Navigation Chamber Earthwork L.Cum 0.49 0.38 77.55 Presently Works on hold and planned to be taken up in Phase-II of the Project.
Navigation Lock/Navigation Chamber Steel mt 618.00 0.00 0.00 None
Navigation Lock/Navigation Chamber Gates mt 55.00 0.00 0.00 None
Irrigation Tunnel Earthwork L.Cum 3.95 3.39 85.82 Second stage benching completed from Ch. 1956 m to Ch. 2780 m.
Irrigation Tunnel Steel mt 3599.17 440.30 12.23 None
Navigation Channel Earthwork L.Cum 2.76 2.59 93.57 None
Navigation Channel Steel mt 0.16 0.00 0.00 On Hold
Exit Channel Earthwork L.Cum 4.22 3.55 83.96 No Progress during the reporting month.
Exit Channel Concrete L.Cum 0.02 0.00 0.00 None
Package No. 66 Saddle Dam KL Embankment L.Cum 21.28 16.18 76.03 Work in progress.
Navigation Tunnel Lining L.Cum 0.56 0.12 21.43 Presently Works on hold and planned to be taken up in Phase-II of the Project.
Saddle Dam KL Earthwork L.Cum 3.09 2.55 82.52 None
Navigation Tunnel Steel mt 898.00 0.00 0.00 None
Exit Channel Earthwork L.Cum 3.09 2.68 86.73 No Progress during the reporting month.
Exit Channel Concrete 500.00 0.00 0.00 None
Saddle Dam KL Concrete 5332.00 2709.00 50.81 No progress during the reporting month.
Depletion Sluice at km 1.575 of Saddle Dam Earthwork 4886.00 4200.00 85.96 No Progress during the reporting month.
Depletion Sluice at km 1.575 of Saddle Dam Concrete 4746.00 441.00 9.29 Concreting in progress.
Depletion Sluice at km 1.575 of Saddle Dam Steel mt 510.00 27.87 5.46 None
Open Cut Earthwork L.Cum 3.98 2.64 66.33 No Progress during the reporting month.
Open Cut Concrete L.Cum 0.02 0.00 0.00 None
Package No. 67 Navigation Canal Lining L.Cum 0.14 0.01 7.14 Presently Works on hold and planned to be taken up in Phase-II of the Project.
Navigation Canal Earthwork L.Cum 7.88 6.33 80.29 None
High Head Locks (1, 2 & 3) Concrete L.Cum 0.75 0.70 92.59 None
High Head Locks (1, 2 & 3) Gates Sqm 1521.56 622.00 40.88 None
LMC Package Wise Package No. 1 Package 1 includes Pkg- 1A: Part work Pkg- 1B: Essential works Pkg- 1C: Non-essential works Earthwork L.Cum 214.00 209.88 98.07 "Package 1 : Terminated /Pre-closed. Package 1(A): Completed."
Package 1 includes Pkg- 1A: Part work Pkg- 1B: Essential works Pkg- 1C: Non-essential works Lining L.Cum 2.50 1.58 63.20 Package 1(B): works in progress.
Package 1 includes Pkg- 1A: Part work Pkg- 1B: Essential works Pkg- 1C: Non-essential works Structures 50.00 25.00 50.00 Package 1(C): Tenders to be called.
Package No. 2 Package 2 Includes Pkg- 2A: NH Crossing near Murari Village (km 33.559) Pkg- 2B: NH Crossing near Mallepalli Village (km 41.56) Earthwork L.Cum 213.27 212.63 99.70 Package 2: Work completed
Package 2 Includes Pkg- 2A: NH Crossing near Murari Village (km 33.559) Pkg- 2B: NH Crossing near Mallepalli Village (km 41.56) Lining L.Cum 2.15 2.13 99.07 Package 2(A): Work restarted
Package 2 Includes Pkg- 2A: NH Crossing near Murari Village (km 33.559) Pkg- 2B: NH Crossing near Mallepalli Village (km 41.56) Structures 42.00 41.00 97.62 Package 2(B): Work completed
Package No. 3 Package 3 Includes Pkg- 3A: Part work Pkg- 3B: Burugupudi NH Crossing Pkg- 3C: Prathipadu NH Crossing Pkg- 3D: Balance essential works Pkg- 3E: Non-essential works Earthwork L.Cum 117.75 109.19 92.73 "Package 3: Terminated /Pre-closed. Package 3(A): Work in progress"
Package 3 Includes Pkg- 3A: Part work Pkg- 3B: Burugupudi NH Crossing Pkg- 3C: Prathipadu NH Crossing Pkg- 3D: Balance essential works Pkg- 3E: Non-essential works Lining L.Cum 1.57 1.32 84.08 "Package 3(B): Work Completed. Package 3(C): Work in progress."
Package 3 Includes Pkg- 3A: Part work Pkg- 3B: Burugupudi NH Crossing Pkg- 3C: Prathipadu NH Crossing Pkg- 3D: Balance essential works Pkg- 3E: Non-essential works Structures 48.00 19.00 39.58 "Package 3(D): Works in progress. Package 3(E): Tenders to be called."
Package No. 4 Package 4 Includes Pkg- 4A: Part work Pkg- 4B: Chendurthi NH Crossing Pkg- 4C: Bendapudi NH Crossing -Pkg- 4D: Arempudi NH Crossing Pkg- 4E: Kathipudi NH Crossing Pkg- 4F: Balance essential works Earthwork L.Cum 131.73 127.35 96.68 "Package 4: Agency has given consent for preclosure of contract. Package 4(A): No progress during the Reporting Month"
Package 4 Includes Pkg- 4A: Part work Pkg- 4B: Chendurthi NH Crossing Pkg- 4C: Bendapudi NH Crossing -Pkg- 4D: Arempudi NH Crossing Pkg- 4E: Kathipudi NH Crossing Pkg- 4F: Balance essential works Lining L.Cum 2.10 1.65 78.57 Package 4(B), 4(C), 4(D) & 4(E): Work in progress during the Reporting Month.
Package 4 Includes Pkg- 4A: Part work Pkg- 4B: Chendurthi NH Crossing Pkg- 4C: Bendapudi NH Crossing -Pkg- 4D: Arempudi NH Crossing Pkg- 4E: Kathipudi NH Crossing Pkg- 4F: Balance essential works Structures 47.00 5.00 10.64 Package 4(F): Agreement concluded on 18-Mar-2025 and work in progress.
Package No. 5 Package 5 Includes Pkg- 5A: Part work Pkg- 5B: Gavarayya Koneru NH Crossing Pkg- 5C: Balance essential works (KM 93.700 to 111.000+0.487KM) Pkg- 5D: Balance non-essential works (KM 93.700 to 111.000+0.487KM) Earthwork L.Cum 204.45 154.42 75.53 "Package 5 & 5(A): Terminated /Pre-closed. Package 5(B): No progress during reporting month."
Package 5 Includes Pkg- 5A: Part work Pkg- 5B: Gavarayya Koneru NH Crossing Pkg- 5C: Balance essential works (KM 93.700 to 111.000+0.487KM) Pkg- 5D: Balance non-essential works (KM 93.700 to 111.000+0.487KM) Lining L.Cum 1.49 0.85 57.05 Package 5(C): works in progress.
Package 5 Includes Pkg- 5A: Part work Pkg- 5B: Gavarayya Koneru NH Crossing Pkg- 5C: Balance essential works (KM 93.700 to 111.000+0.487KM) Pkg- 5D: Balance non-essential works (KM 93.700 to 111.000+0.487KM) Structures 47.00 11.00 23.40 Package 5(D): Tenders to be called.
Package No. 6 Package 6 components: Pkg- 6A: Part work Pkg- 6B: Balance essential works Pkg- 6C: Balance non-essential works Pkg- 60C: Balance leftover earthwork quantity Structures 83.00 24.00 28.92 Package 6 60(C): Work in progress.
Package 6 components: Pkg- 6A: Part work Pkg- 6B: Balance essential works Pkg- 6C: Balance non-essential works Pkg- 60C: Balance leftover earthwork quantity Earthwork L.Cum 169.12 143.49 84.85 "Package 6: No progress during the reporting month. Package 6(A): Terminated/Pre-closed."
Package 6 components: Pkg- 6A: Part work Pkg- 6B: Balance essential works Pkg- 6C: Balance non-essential works Pkg- 60C: Balance leftover earthwork quantity Lining L.Cum 2.06 1.50 72.82 "Package 6(B): Works in progress. Package 6(C): Tenders yet to be called."
Package No. 7 Package 7 Earthwork L.Cum 100.83 99.52 98.70 None
Package 7 Lining L.Cum 1.87 1.70 90.91 None
Package 7 Structures 68.00 38.00 55.88 Work in progress.
Package 7(A) Earthwork L.Cum 51.73 51.73 100.00 None
Package No. 8 Package 8 components: Pkg- 8A & 8B: Part works Pkg- 8C: Balance essential works Pkg- 8D: Balance non-essential works Pkg- 8E: Pisinikada NH Crossing Pkg- 8F: Railway Crossing Earthwork L.Cum 24.79 17.85 72.00 "Package 8, 8(A) & 8(B): Terminated/pre-closed. Package 8(C): Agreement for balance essential works concluded"
Package 8 components: Pkg- 8A & 8B: Part works Pkg- 8C: Balance essential works Pkg- 8D: Balance non-essential works Pkg- 8E: Pisinikada NH Crossing Pkg- 8F: Railway Crossing Lining L.Cum 0.88 0.23 26.14 "Package 8(D): Tenders yet to be called. Package 8(E): Contract award to be done"
Package 8 components: Pkg- 8A & 8B: Part works Pkg- 8C: Balance essential works Pkg- 8D: Balance non-essential works Pkg- 8E: Pisinikada NH Crossing Pkg- 8F: Railway Crossing Structures 76.00 3.00 3.95 Package 8(F): GAD approved and estimates to be prepared and submitted.
RMC Package Wise Package No. 1 Package 1 Earthwork L.Cum 167.75 167.75 100.00 Work completed
Package 1 Lining L.Cum 1.61 1.61 100.00 None
Package 1 Structures 24.00 24.00 100.00 Package 6 60(C): Work in progress.
Package No. 2 Including Package 2 & Package 2 60(C) Earthwork L.Cum 203.46 203.46 100.00 None
Including Package 2 & Package 2 60(C) Lining L.Cum 3.28 3.09 94.21 No progress during this month
Including Package 2 & Package 2 60(C) Structures 31.00 28.00 90.32 None
Package No. 3 Including Package 3 & Package 3 60(C) Earthwork L.Cum 234.79 234.79 100.00 Package 3: Work completed
Including Package 3 & Package 3 60(C) Lining L.Cum 3.07 3.07 100.00 Package 3 60(C): No progress during the Reporting Month
Including Package 3 & Package 3 60(C) Structures 39.00 38.00 97.44 Work in progress.
Package No. 4 Including Package 4 & Package 4 60(C) Earthwork L.Cum 219.20 219.20 100.00 Package 4: Work completed
Including Package 4 & Package 4 60(C) Lining L.Cum 3.66 3.64 99.45 Package 4 60(C): Work in Progress during the reporting month
Including Package 4 & Package 4 60(C) Structures 45.00 44.00 97.78 None
Package No. 5 Including Package 5 & Package 5 60(C) Earthwork L.Cum 124.19 124.19 100.00 None
Including Package 5 & Package 5 60(C) Lining L.Cum 2.96 2.67 90.20 No progress during this month
Including Package 5 & Package 5 60(C) Structures 54.00 35.00 64.81 None
Package No. 6 Including Package 6 & Package 6 60(C) Earthwork L.Cum 116.94 116.94 100.00 None
Including Package 6 & Package 6 60(C) Lining L.Cum 2.23 2.04 91.48 No progress during this month
Including Package 6 & Package 6 60(C) Structures 34.00 22.00 64.71 None
Package No. 7 Package 7 Earthwork L.Cum 66.61 66.61 100.00 Work completed
Package 7 Lining L.Cum 1.03 1.03 100.00 None
Package 7 Structures 15.00 15.00 100.00 None
Package 7(A) Lining L.Cum 1.42 0.90 63.38 No progress during this month
Package 7(A) Structures 13.00 8.00 61.54 None

Financial Progress


Financial Progress of Polavaram Irrigation Project (PIP)
S. No. Component (%) Progress*
1 Connectivities 64.40
2 Right Main Canal 92.77
3 Left Main Canal 60.76
4 Total civil works 76.39
5 LA&RR (Excluding Rs. 2500 Cr. CM assurance) 25.17
6 Overall Project Progress (as per agreement values excluding Rs. 2500 Cr. towards CM Assurance) 40.48
7 Overall Project Progress (as per RCC @2017-18PL) 56.86
8 Headworks 79.38
* as reported by WRD,GoAP
**Headworks percentage reduced due to conclusion of new agreement for scour treatment in main dam

Details of Rehabilitation and Resettlement under Phase- I (EL + 41.15 M)
S. No. Particulars Total
1 Total Land to be Acquired in Phase-I (In Acres) 100100.00
2 Fund required for LARR in Phase-I (Rs. in Cr.) 12270.42
3 Total Affected Habitations (Nos.) 172.00
4 Total No. of PDFs to be shifted in Phase-I (Nos.) 38060.00
5 Total R&R Colonies (Nos.) 121.00


Balance PDFS to be Shifted under Phase-I (EL + 41.15 M)
S. No. Target of Month Target of Shifting Progress % Shifted Monthly Backlog Cumulative Backlog
1 Apr-23 6999 0 0.00 6999 6999
2 May-23 1554 872 56.11 682 7681
3 Jun-23 556 109 19.60 447 8128
4 Jul-23 160 0 0.00 160 8288
5 Aug-23 6858 0 0.00 6858 8288
6 Sep-23 1430 0 0.00 1430 8288
7 Oct-23 855 0 0.00 855 8288
8 Nov-23 2700 0 0.00 2700 8288
9 Dec-23 4733 139 5.15 2561 8149
10 Jan-24 855 0 0.00 855 8149
11 Feb-24 2700 0 0.00 2700 8149
12 Mar-24 4594 0 0.00 4594 8149
13 Apr-24 855 0 0.00 855 8149
14 May-24 2700 0 0.00 2700 8149
15 Jun-24 4594 0 0.00 4594 8149
16 Jul-24 855 0 0.00 855 8149
17 Aug-24 2700 0 0.00 2700 8149
18 Sep-24 4594 0 0.00 4594 8149
19 Oct-24 855 0 0.00 855 8149
20 Nov-24 2700 0 0.00 2700 8149
21 Dec-24 4594 0 0.00 4594 8149
22 Jan-25 855 0 0.00 855 8149
23 Feb-25 2700 1566 58.00 1134 6583
24 Mar-25 4594 0 0.00 0 0
Reimbursement details w.r.t Revised cost for completion of the Polavaram Irrigation Project (PIP) with water storage up to EL +41.15 metres i.e. Minimum Draw Down Level
S. No. Particulars As per RCC Report @ 2023 PL (in Rs Cr.)
1 Revised Cost of Phase-I of the project @ 2023 PL 30436.95
2 Expenditure made on project before declaration of project as National Project.(before 01.04.2014) 4730.71
3 Balance to be reimbursed by Govt. of India (Eligibility of GoAP) (1-2) 25706.24
4 Total amount reimbursed by Government of India after the project declared as National Project 15605.96
5 Reimbursement made towards LA and R&R activities above MDDL 1597.56
6 Reimbursed made by Government of India for the Phase-I of the Project (4-5) 14008.40
7 The balance amount for Phase-I of the Project (3-6) 11697.84


Funds Released by Govt. of India (Rs in Cr.)
As on: 31-05-2025
S.No. Financial Year Funds released by GoI
(Rs in Cr.)
Date of Release Remarks
1 2014-15 1.00 09-03-2015
249.00 30-03-2015
2 2015-16 100.00 09-07-2015
300.00 11-02-2016
200.00 31-03-2016
3 2016-17 100.00 04-08-2016
1981.00 23-12-2016
433.16 31-03-2017
4 2017-18 979.36 30-08-2017
318.22 11-12-2017
284.98 24-01-2018
417.44 07-02-2018
5 2018-19 1089.07 04-05-2018
310.93 31-05-2018
6 2019-20 1850.00 09-01-2020
7 2020-21 2234.20 04-12-2020
8 2021-22 333.00 04-05-2021
418.80 09-07-2021
320.00 04-01-2022
391.00 10-03-2022
436.00 31-03-2022
9 2022-23 297.99 13-07-2022
180.90 27-10-2022
366.17 21-03-2023
826.18 28-03-2023
10 2023-24 550.97 20-06-2023
143.38 17-10-2023
33.53 26-10-2023
11 2024-25 76.46 09-10-2024
383.23 09-10-2024
Total Releases 15605.97
  • PPA 2254.88
  • CWC 2254.88
  • DoWR, RD&GR 2254.88
  • MoF 2254.88
Polavaram Irrigation Project
Details of Current Bills and its Reimbursement by Authorities
(PPA→CWC→DoWR,RD&GR→MoF)
in Rs. Crs.
S.No. Eligible bills forwarded by PPA to CWC Bills Forwarded by CWC to DoWR,RD&GR Bills Forwarded by DoWR,RD&GR to MoF Amount Approved by MoF
Date Amount Date Amount Date Amount Date Amount
1 20-01-2025 2254.88 28-01-2025 2254.88 2254.88 2254.88
Total 2254.88 2254.88 2254.88 2254.88
* Note: PPA - Polavaram Project Authority
   CWC - Central Water Commission
   DoWR, RD&GR - Department of Water Resources, River Development & Ganga Rejuvenation
   MoF - Ministry of Finance